Exam PK0-005: CompTIA Project+
Exam Number: PK0-005 | Length of test: 90 mins |
Exam Name: CompTIA Project+ | Number of questions in the actual exam: 55-90 |
Format: PDF, VPLUS | Passing Score: 6++/900 |
Total Questions: 299 $30 Premium PDF file 2 months updates Last updated: March-2025 |
![]() Total Questions: 299 FREE Premium VPLUS file Last updated: March-2025 |
Download practice test questions
Title | Size | Hits | Download |
---|---|---|---|
CompTIA.PK0-005.vOct-2024.by.Alanty.148q | 744.99 KB | 35 | Download |
CompTIA.PK0-005.vOct-2024.by.Alanty.148q | 548.77 KB | 35 | Download |
CompTIA.PK0-005.vJan-2024.by.Jacky.86q | 1.21 MB | 77 | Download |
CompTIA.PK0-005.vMar-2024.by.SamB.107q | 598.56 KB | 78 | Download |
Some new sample questions:
Question:
A project manager hired a vendor to perform some of the critical-path activities for a project. The vendor missed two deadlines and is insisting on receiving full payment. Which of the following should the project manager do to address this issue?
A. Review the vendor deliverables
B. Escalate to the steering committee
C. Enforce vendor rules of engagement
D. Agree to compromise with the vendor
Question:
Which of the following best describes the meaning of timeboxing in the context of a project kickoff meeting?
A. Allowing a discussion to proceed until a decision is made
B. Allowing the meeting attendees more time for deeper conversation
C. Allowing for a flexible timeline so all aspects of the project are covered
D. Allowing a conversation to continue for a predefined period of time
Question:
A project team member has been interacting on personal social media instead of performing assigned tasks. This behavior is explicitly forbidden in the team charter. Which of the following actions should the project manager take?
A. Address the issue at the next team meeting to allow other team members to provide feedback
B. Conduct an informal meeting with the team member to discuss work assignments and obstacles
C. Allow the team member to continue to use personal social media during times of productivity
D. Post a copy of the team charter on the file-sharing platform and encourage interactive discussions
……….
Some new questions:
Q
A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?
A. Performance
B. Smoke
C. Regression
D. Unit
Q
During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?
A. Hold a new backlog prioritization meeting.
B. Add milestones to check the project’s progress.
C. Adjust the task relationship to complete coding in advance.
D. Apply contingency buffers to the critical path.
Q
A client made a change request. Implementing the change will cause a delay in the project and a budget overrun. Which of the following should the project manager do first?
A. Update the WBS.
B. Escalate to the CCB.
C. Accept the change.
D. Implement the change.
Q
Which of the following statements best represents a network issue?
A. The development team on the fourth floor is unable to access servers and email services.
B. Cell phones served by a specific telecom company are getting a ‘no service’ message.
C. A user cannot connect to Wi-Fi because of a wrong ID or password.
D. A user is receiving an automatic reply message saying that an email address does not exist.
……….